Scope of supply
UTB built the extension to the industrial wastewater treatment plant at ATEV’s animal by-product processing works in Mátyásdomb. The line combines physico-chemical treatment and dissolved air flotation with CYCLATOR-U™ biological treatment and two BIODEC™ S 100 decanters.
- 300 m³/day
- 14,307 PE
- Physico-chemical · DAF · CYCLATOR-U · BIODEC S 100 ×2
- Industrial WWTP extension
- Completed 2018.
| Client | ATEV Zrt. |
| Location | Mátyásdomb, Hungary |
| Segment | Industrial |
| Capacity | 300 m³/day |
| Technologies | BIODEC S 100, CYCLATOR-U |
On site