Balástya

Balástya, Hungary

CYCLATORBIODECMunicipal
Operations building at the Balástya municipal wastewater treatment plant, Hungary

Scope of supply

UTB delivered the municipal wastewater treatment plant at Balástya built on CYCLATOR™, with BIODEC™ S 100 ×2 decanters, completed 2014.

  • 250 m³/day
  • 3,678 PE
  • CYCLATOR · BIODEC S 100 ×2
  • Communal STP
  • Completed 2014.
ClientPROBART Kft.
LocationBalástya, Hungary
SegmentMunicipal
Capacity250 m³/day
TechnologiesCYCLATOR, BIODEC

Parameters as commissioned

Influent, the consent limit, and the effluent quality actually measured.

 
Parameter Influent (mg/l) Effluent Limit (mg/l) Effluent Quality (mg/l)
CODKr 1,766 75 45
BOD5 883 25 7.7
TN 162 50 15
NH4-N 108 10 1
TSS 1,035 50 30
TP 27 5 3.2