Nyírszőlős, KELET-FOOD 2000

Nyírszőlős, Hungary

UASBIndustrial
Treatment building at the KELET-FOOD legume and corn processing wastewater plant, Nyírszőlős, Hungary

Scope of supply

UTB built the plant treating effluent from legume and corn processing at KELET-FOOD 2000 in Nyírszőlős, turnkey. The line runs a drum filter, equalisation, pH adjustment and nutrient dosing, then a heat exchanger into a UASB biological reactor, with sludge collection and a biogas system behind it.

  • 350 m³/day
  • 47,833 PE
  • 2,150 Nm³/day biogas
  • UASB anaerobic reactor
  • Effluent from legume and corn processing
  • Completed 2005.
ClientKELET-FOOD 2000
LocationNyírszőlős, Hungary
SegmentIndustrial
Capacity350 m³/day
TechnologiesUASB

Parameters as commissioned

Influent, the consent limit, and the effluent quality actually measured.

Parameter Unit Influent Effluent
COD mg/l 12,856 1,800
TSS mg/l 1,705 600

On site

Treatment building at the KELET-FOOD legume and corn processing wastewater plant, Nyírszőlős, HungaryTreatment building at the KELET-FOOD legume and corn processing wastewater plant, Nyírszőlős, Hungary